It is the objective of the HVAC engineer
to design the most cost-effective pumping system while meeting the clients needs.
Primary-secondary pumping is a tool HVAC engineers have been using for nearly 50 years to
accomplish this objective.

ASHRAE/IES Standard 90.1-1989Energy Efficient Design
of New Buildings Except Low-Rise Residential Buildingsrequires all pumping
systems with modulating or step open and closed valves which have total pump system
horsepower 10 must be capable to flow at 50 percent of design value or less. The
Standard 90.1-1989 Users Manual highly recommends primary-secondary
pumping for systems with large, high pressure drop distribution systems such as
those serving campuses and airports.
Primary-secondary pumping (Fig. 1) provides the means for
the constant volume pumping of the low horsepower primary pumps through the chiller. These
pumps are lower horsepower than the secondary pumps because they only have to overcome the
friction loss associated with the chiller, pipes, and valves in the primary loop. The
chiller pumps are balanced to the design flow rate. Pump impellers should be trimmed to
minimize the pressure drop across the valve on the discharge of the pump. This is an
important energy saving measure.
The secondary pumps are higher
horsepower because they must overcome the friction loss associated with the secondary
loopthe distribution piping, fittings, valves, coils, etc. These pumps operate in
the energy saving variable volume mode. Depending on the return on investment, the
secondary pumps either remain constant speed and ride their characteristic head-capacity
curve, or the designer can incorporate adjustable frequency drives to save additional
pumping energy (Fig. 2).
There are three critical design areas that must be
considered for any variable volume pumping system:
- The common pipe
- Chiller sequencing
- Control valves and actuators
Common pipe design
The design of the common pipe (Fig. 3) is critical to the
performance of a primary-secondary system. The function of the common pipe is to decouple
hydraulically the primary and secondary pumps while still providing thermal interaction.
To ensure proper system performance, the common pipe design criteria are:
The maximum pressure drop in the common pipe shall not
exceed 1.5 ft Establish the pressure drop in the common pipe by assuming the flow of
the largest chiller pump is passing through the common pipe. The resultant pressure drop
should not exceed 1.5 ft. This is the basis of primary-secondary pumping. Higher friction
loss in the common tends to make the primary and secondary pumps act in series, resulting
in an induced flow in the system. (This incorporates a safety factor.) Typically, a
chiller is usually sequenced on or off by the time one half of the flow of the largest
pump is achieved. For simplicity of design and installation, the common pipe is often the
same diameter as the distribution piping.
Maintain three pipe diameters of separation between
the secondary supply tee and the secondary return teeA common pipe of this length is
more than adequate to eliminate mixing due to excessive return velocity in the secondary
return piping. Longer length common pipes may result in an excessive pressure drop greater
than 1.5 ft with results as described above.

Under no circumstances should a check valve be located in a
common pipe. The addition of a check valve will result in the primary and secondary pumps
acting in series when secondary (distribution) flow exceeds primary (production) flow. The
increase in demand results in an increase in flow through the chiller that can lead to
higher chiller discharge temperatures and chiller tube erosion. Further details on this
subject are discussed below in the chiller sequencing section.
Other terms are often used interchangeably when discussing
primary-secondary pumping. The primary system is also known as the production
systemthe place where the chilled or hot water is produced.
The secondary system is also called the distribution system
because its purpose is to convey the chilled and hot water to and from the load(s).
The common pipe is also known as a decoupler. This
pipecommon to both the primary and secondary systems provides the hydraulic
separation between the two.
Chiller sequencing
Proper chiller sequencing plays an important role in the
overall performance of a primary-secondary pumping system. The operator of the system must
recognize the three flow conditions that can occur. These are:
Distribution (secondary) flow equals production
(primary) flow.
Distribution flow is greater than production flow.
Production flow is greater than distribution flow.
Distribution flow equals production flowAlthough
this flow condition rarely occurs, we will observe the flow pattern of this scenario (Fig.
4). The chiller is supplying 1500 gpm of 45 F water to the load system. The two-way valves
in the secondary are responding to conditions equal to 1500 gpm x 10 F Delta T x 500 = 7.5
MBtuh or 625 tons. The two-way valves, coils, and associated piping represent a pressure
drop of 100 ft. The secondary pump is riding its curve, producing the required 1500 gpm at
100 ft of head. Because the load is equal to 625 tons, the return water temperature to the
chiller is 55 F at a flow rate of 1500 gpm. The thermal balance is complete. There is no
flow in the common pipe.

The remainder of the time of the secondary or load flow
will be greater or less than the primary flow. The moment the load increases in the space,
the two-way valves begin modulating to a more open position and deliver additional chilled
water to satisfy the additional load. When this occurs, the pressure and flow relationship
changes such that the distribution flow is greater than the production flow (Fig. 5).

Distribution flow greater than production
flowWith this condition, the flow rate through the chiller is 1500 gpm at 45 F.
Because the flow rate is fixed at 1500 gpm, the pressure drop in the primary loop is
constant. As the load increases in the secondary and the two-way valves modulate open in
response, the secondary pumps run out on their curves to provide additional flow. As the
secondary pumps run out on their curves corresponding to the reduced pressure, flow
increases to the required 2000 gpm. If 2000 gpm is flowing into the secondary, 2000 gpm
must return from the secondary. The balanced chillers will only accept 1500 gpm.
To balance the mass flow, the excess 500 gpm must run
through the common pipe. The temperature of the 500 gpm in the common pipe is 55 F. This
blends with the 1500 gpm of 45 F supply water, resulting in 2000 gpm of 47.5 F blended
supply water.
Whenever the flow is greater in the distribution loop than
in the production loop, the excess flow in the common pipe is in the direction towards the
secondary pumps. The result will always be a blending of the return water with the supply
water at a temperature higher than what the chiller produces. What will happen to the
temperature control? A higher supply water temperature could mean a loss of humidity
control in the zones. Higher supply water temperatures must be considered during the coil
selection process.
Other options can be considered. For example, chiller
temperature reset can be employed. Within the limits of the type of machine, chiller
temperatures can be reset to a lower temperature to compensate for the increased load and
secondary flows. In essence, more capacity is provided at a lower operating efficiency.
The increase in cost of chiller operation due to the lowering of the chiller supply
temperature can range from 1 to 3 percent per degree of reset. This is a very desirable
alternative, especially when large chillers are in use. The longer the start of a lag
chiller can be delayed, the better it will perform when it is finally brought on line. If
a small portion of the load requires a fixed temperature, a small chiller in series with
the load may also be considered.
Production flow greater than distribution When
incremental chiller capacity is added, the third flow condition occurs (Fig. 6). The flow
rates through the chillers are again fixed, this time at 3000 gpm. The new load is 875
tons. As we are again seeing a 45 F supply water temperature and a 55 F return water
temperature, the flow rate for the secondary pump is 2100 gpm. With 2100 gpm delivered to
the secondary and 3000 gpm being pumped in the primary loop, there is an excess flow of
900 gpm. The 900 gpm excess must flow through the common pipe at the chilled water supply
temperature of 45 F. The 900 gpm common flow blends with the 2100 gpm secondary chilled
water return to produce 3000 gpm at a reduced entering chilled water temperature of 52 F.

All chilled water returning to the chilled water plant is
blended prior to reaching the chillers. All of the chillers on line will therefore be
receiving the same temperature water at their return. When the system is piped in this
manner, the chillers will always be equally loaded. Furthermore, the chillers will always
be subjected to their design flow at an equal temperature. Because the chillers are
receiving their design flow rate at 52 F rather than the design temperature of 55 F, the
chillers will be unloaded at the ratio of:

When piped with a common, the flow through the chillers is
a constant. In our example, the two steps are either 50 percent flow (1500 gpm) or 100
percent flow (3000 gpm). The secondary flow is very close to a linear
function. As the two-way valves modulate in response to a varying load, the flow
follows directly. The more chillers in the plant, the smaller the steps. If we incorporate
chillers in a variety of sizes, the incremental steps are smaller. The additional chillers
and variety of chiller sizes can produce a curve that is nearly linear. When the chiller
plant is designed to produce a near-linear flow function, the supply temperature rises,
the secondary is minimized, and the increased supply water temperature lasts for a shorter
duration. This is a very critical factor in design regions where humidity control is a
concern.
Chiller sequencing can be as simple as manually turning on
and off a second chiller. It can also become complex when multiple chillers of different
sizes, types, and efficiency are installed. The chiller manufacturer is usually best
suited to provide the information and instrumentation to effectively stage and de-stage
its product.
Conceptually, the designer needs to determine the best
combination of chillers that will meet the flow demand. This is often done by calculating
the Btuh consumed (Fig. 7). Instrumentation must be provided to determine:
Secondary supply water temperature, Ts-s
Secondary return water temperature, Ts-r
Secondary flow, Fs

The amount of cooling Btuh produced is also valuable
information. The necessary instrumentation is: n Primary supply water temperature (chiller
leaving), T p-s n Primary return water temperature (chiller entering), Tp-r
Primary flow (chiller flow), F p
An algorithm is then prepared, which utilizes the best
combination of chillers for the actual load. The measurement of flow and direction in the
common pipe does not provide the operator with enough information to determine the time of
sequencing. The same can be said for the measurement of flow in the secondary system.
Control Valves and Actuators
Control valves are a critical part of the variable volume
hydronic system. The control valves functions are to vary flow properly through the
water coil in response to a variety of building load conditions. Because of their critical
nature, great care must be taken when selecting control valves so they perform properly.
Undersized valves may provide insufficient capacity while oversized valves provide poor
control.
Equal percentage type valves are typically applied to
cooling and heating coils because of their favorable flow characteristic. They provide a
high degree of control accuracy with wide variations in pressures, flow rates, loads, and
other variables. When combined with the heat transfer characteristic of a cooling coil,
the change in stem position almost provides a nearly linear change in heat transfer if an
equal percentage control valve is used.
Knowing the maximum differential pressure across the valve
at any flow is an important criterion for valve selection for two reasons (Fig. 7):
Choosing the appropriate actuator
Avoiding valve noise and cavitation in valves and
piping
In variable volume systems, the selected valve actuator
must be capable of closing the valve against the maximum pump head pressure (Fig. 8). In
variable volume closed loop systems, all loads could be reduced causing the pump to ride
back on the pump curve. As the pump rides back on the curve, the head being produced by
the pump increases. The control valve actuator must be strong enough to continue
modulating the valve closed as the pressure increases. In the worst case, this could be
the shutoff pressure being produced by the pump. Improper actuator sizing may
result in some water passing through the valve and coil, which add to low return water
temperatures.

Excessive valve noise and valve cavitation are caused by
high liquid velocities. As water passes through a valve, it is accelerated. With the
increase in velocity pressure, the static pressure falls. If it drops below the vapor
pressure, bubbles form. Then immediately downstream of the valve, velocity decreases and
the static pressure increases, causing the bubbles to collapse. The result is noise
coupled with excessive wear in the valve body, throttling mechanisms, and sometimes in the
downstream piping where this takes place.
When variable speed secondary pumping is employed, valves
are normally subjected to less differential pressure. In this mode, the pump follows the
characteristic control curve ential pressure when conditions are at less than maximum
design. Care must still be taken if an across-the-line (ATL) adjustable frequency drive
bypass (electrical bypass) is used. When the system functions in the ATL mode, the pump
acts like a constant-speed pump. It is now following the pump flow-head curve at a much
higher pressure. The designer may overlook this condition. Under low flow conditions, the
valves may lift up as described earlier. If the selected actuators have inadequate holding
power at the higher head shut-off condition, the valves may lift up as previously
described.
Three-way valves have little use in variable volume pumping
systems. Three-way valves bypass unused chilled water past the load; this results in
multiple problems. Bypassed water lowers the return water temperature and increases flow
rates. As a result, additional chillers and pumps are brought on-line to provide flow,
rather than to control the cooling load.
A circumstance where three-way valves can be used
(carefully) in the system is to maintain minimum flow as a means of pump protection. As a
rule of thumb, the Hydraulic Institute and ITT Fluid Handling recommend a minimum flow
rate of 20 percent of the best efficiency point flow rate. To limit the radial and axial
loads and shaft deflection, our recommendation is to maintain a minimum flow rate of 25
percent of the best efficiency point flow rate.
The Hydraulic Institute and ITT Fluid Handling also
recommend limiting the temperature rise of the fluid flowing through the pump to 15 F.
(This is not to be confused with the system temperature rise.) When a pump is operating in
a low flow condition, the temperature rise occurs in a small volume of water. If an
insufficient volume of water flows through a pump, the inefficiency of the pump is
converted to heat. In time, the heat build-up can cause the fluid to vaporize and
eventually result in To calculate the flow rate for a 15 F temperature rise use the
following equation:

When careful attention is given to these fundamentals,
energy savings will be achieved and design system Delta T will be achieved. As system
characteristics change due to load changes, the aging of the piping and coils, or even as
coils get dirty, system Delta T may suffer. There is no substitute for knowledgeable
operators and proper maintenance schedules. The adjustment of thermostats and the lowering
of supply air temperatures will only add to the inefficiency. Unless problems are cured,
only patches can be applied to treat symptoms. Fixes consume additional
energy. The only way to keep a properly designed HVAC system operating efficiently is to
maintain it in the appropriate manner.
Conclusion
To optimize system performance and design flexibility, the
designer must select the type of distribution piping and pumping configuration that will
best meet the needs of the client. The following are the four basic types of pumping
systems in use today.
Primary-secondary
Primary-secondary-tertiary
Primary-secondary zone
Primary variable speed
These pumping methods will be discussed in the next issue
of Tech Talk.
This article was originally published in the August 1998
issue of Heating/Piping/Air Conditioning magazine.
Reprinted from TechTalk January 1999
Copyright 1999 by ITT Industries |